The power line that could reshape New York’s grid is hitting snags

0
NKT_CHPE-6_2.jpg

Some experts say this isn’t unusual for a new infrastructure project. Other power lines have seen similar startup challenges, and the equipment hasn’t really been fully tested until it’s in operation, Normand Mousseau, a physics professor at Université de Montréal, told the Gazette.

Officials traced the issue to a damaged section of cable on the US side of the border, and the company that manufactured the line sent experts to investigate the cause, according to reporting from RTO Insider, a trade publication. 

The damaged portion of the cable has been removed and replaced, says Lynn St-Laurent, a spokesperson for Hydro-Québec. “It is currently estimated that the remaining work, including necessary post-repair testing, will be completed by the weekend.”

Similar woes have afflicted the New England Clean Energy Connect line, which opened in January, stretching 145 miles from Quebec to Maine. That project has also seen outages, and very little additional energy has flowed into the Northeast.

The good news for New York is that the grid wasn’t relying on CHPE yet. “Our planning studies did not assume CHPE would be available this summer, and that was one reason the grid performed reliably during the heat wave earlier this month,” Kevin Lanahan, a spokesperson for the New York Independent System Operator, the state’s grid management company, said in a statement. “A core principle of reliability planning is not relying on any single project.” 

The idea is that eventually, states and regions will be able to rely—at least in part—on these projects, so there is pressure to get them working smoothly: Building massive transmission lines is a major long-term investment. In future years, as the equipment gets stress-tested and utilities begin to feel more confident in the projects’ reliability, they could play a bigger role on the grid.

One thing to keep an eye on moving forward is the condition of Quebec’s hydropower fleet: The region has seen intense drought for the past three years, eating into the water reserves used to generate electricity. That could mean there won’t always be abundant hydropower to ship across the border—even if the transmission lines are able to carry it. 

This article is from The Spark, MIT Technology Review’s weekly climate newsletter. To receive it in your inbox every Wednesday, sign up here

#power #line #reshape #Yorks #grid #hitting #snags